Participating Churches
Project Leader David Benson
House Leader Monte Morgan
Family Partners Lucy Freeman & Lucy Krieg
The following were the thirteen St. Louis area churches that participated in the 1999 Episcopal Habitat Project, with further support from the Episcopal Diocese of Missouri.
| Episcopal Church of the Advent, Crestwood |
St. Mark's Episcopal Church, St. Louis |
| All Saints' Episcopal Church, St. Louis |
St. Martin's Episcopal Church, Ellisville |
| Christ Church Cathedral (Episcopal), St. Louis |
Episcopal Church of St. Michael & St. George, Clayton |
| Emmanuel Episcopal Church, Webster Groves |
St. Peter's Episcopal Church, Ladue |
| Good Shephard |
St. Timothy's Episcopal Church, Creve Coeur |
| Grace Episcopal Church, Kirkwood |
Trinity Episcopal Church, St. Charles |
| Episcopal Church of the Holy Communion, University City |
Trinity Episcopal Church, St. Louis |
| Episcopal Diocese of Missouri |
Final 1999 Build Schedule
Here's the history of our 1999 Habitat build. Click on the dates below to see the story in pictures!
| Date |
Week |
Tentative Task |
Churches |
Crew Size |
Lunch |
| Jun 26, 99 |
1 |
Subfloor |
Holy Communion
Grace
Advent |
9
5
4 |
Advent |
| Jul 10, 99 |
2 |
Subfloor |
Cathedral
St. Timothy
Trinity - St. Charles |
6
6
7 |
Cathedral |
| Jul 17, 99 |
3 |
Exterior Walls
|
Emmanuel
St. Martin
St. Michael/St. George
St. Mark |
7
5
6
3 |
Emmanuel |
| Jul 24, 99 |
4 |
Interior Walls |
Trinity - St. Louis
Holy Communion
All Saints |
5
8
6 |
Trinity - St. Louis |
| Jul 31, 99 |
5 |
Roof Trusses, Roof Sheets, Windows |
Cathedral
St. Timothy
Good Shepard |
7
6
8 |
St. Timothy |
| Aug 7, 99 |
6 |
Roof Sheets, Blue Board, Exterior Doors |
Emmanuel
St. Martin
All Saints |
7
5
7 |
St. Martin |
| Aug 14, 99 |
7 |
Roof Sheets, Siding, Stairs |
Holy Communion
Grace
Trinity - St. Charles |
9
5
7 |
Grace |
| Aug 21, 99 |
8 |
Siding, Soffits |
Cathedral
St. Michael/St. George
St. Mark |
6
7
4 |
St. Michael/St. George |
| Aug 28, 99 |
9 |
(Cancelled - Moved to Nov 6) |
|
|
|
| Sep 11, 99 |
10 |
Drywall Ceilings |
Holy Communion
St. Martin
All Saints |
9
5
6 |
All Saints |
| Sep 18, 99 |
11 |
Drywall Walls |
St. Peter's Youth
|
|
St. Peter |
| Sep 25, 99 |
12 |
Floor Underlayment |
Emmanuel
St. Timothy
Grace
|
7
6
5 |
St. Timothy |
| Oct 2, 99 |
13 |
Paint Walls |
Cathedral
Trinity - St. Charles
Trinity - St. Louis |
6
6
5 |
Trinity - St. Charles |
| Oct 9, 99 |
14 |
Paint Walls, Ceilings |
Holy Communion
Advent
Good Shepard |
8
5
7 |
Holy Communion |
| Oct 16, 99 |
15 |
Floor Tile |
Cathedral
Emmanuel
St. Timothy |
6
7
6 |
Emmanuel |
| Oct 23, 99 |
16 |
Install Baseboards, Shelves Hardware, Doors |
St. Michael/St. George
Trinity - St. Louis
Trinity - St. Charles |
6
5
6 |
Trinity - St. Charles |
| Oct 30, 99 |
17 |
Kitchen Cabinets, Final Paint |
St. Peter
Good Shepard
St. Mark |
5
8
3 |
St. Peter |
| Nov 6, 99 |
18 |
Punch List |
Trinity - St. Louis
Good Shepard
Advent |
8
7
4 |
Good Shepard |
Dedication
The dedication was held on December 12, 1999 at the Friendly Temple Church at the corner of Burd and Martin Luther King.
The dedication was for several houses completed near the end of 1999.
After the combined service our group gathered at the house for our own ceremony.
Click here for images from the dedication.
|