The following were the thirteen St. Louis
area churches that participated in the 2002 Episcopal Habitat Project, along
with Citigroup units Citimortgage, Travelers Insurance, and Salomon Smith
Barney.
| Episcopal Church of the Advent, Crestwood |
St. Mark's
Episcopal Church, St. Louis |
| Christ Church Cathedral (Episcopal), St. Louis |
St. Martin's
Episcopal Church, Ellisville |
| Emmanuel Episcopal Church, Webster Groves |
Episcopal Church
of St. Michael & St. George, Clayton |
| Grace
Episcopal Church, Kirkwood |
St. Peter's Episcopal Church, Ladue |
| Episcopal Church of the Holy Communion, University
City |
St. Timothy's
Episcopal Church, Creve Coeur |
| St. Luke's Episcopal Church, Manchester |
Trinity
Episcopal Church, St. Charles |
| Trinity Episcopal Church, St. Louis |
2002 Photo Gallery
June 22 - A
hole in the ground
July 13 -
A foundation on which to build
July 20 -
First story walls
July 27 -
Second story joists & subfloor
August 3
- Second story walls
August 10
- Second story walls and rock removal
August 17
- Windows, 2nd story interior walls, roof joists and deck
September
7 - Insulation, drywall, and siding
September
14 - More drywall and siding.
September
21 - "More more" drywall and siding.
September
28 - Subfloor and siding.
October 5
- Floor tile and cornice work.
October 12
- Floor tile, stairwell, and cabinetry.
October 19
- Painting, trim, and fencing.
October 26
- Fencing, tree removal, odds and ends.
November
2 - Fencing, tree planting, trim work.
November
9 - Sod.
November
16 - Dedication!
Dedication
The dedication was held
on November 16, 2002 at the Met Center.
The dedication was for several houses completed
near the end of 2002.
After the combined service our group gathered
at the house for our own ceremony and blessing, conducted by Reverend Brooke
Myers of Holy Communion
Click here for images from the dedication.
|